§ 8.36.100. Liability for costs for performance of work required by order.
When action required by an order is performed by the enforcement authority or by a contractor acting under Section 11 of I.C. 36-7-9, each person who held a fee interest, life estate interest, or equitable interest of a contract purchaser in the unsafe premises from the time when the order requiring the work performed was recorded to the time that the work was completed is jointly and severally responsible for the costs set forth at I.C. 36-7-9-12(a)(1) and (2).
Costs shall be determined on the basis of the factors listed in I.C. 36-7-9-12. If all or any part of the costs listed in I.C. 36-7-9-12 remain unpaid for any unsafe premises for the time period set forth at I.C. 36-7-9-13, the enforcement authority shall proceed pursuant to I.C. 36-7-9-13 and I.C. 36-7-9-13.5.
(Ord. 05-01 § J)